The project entailed the structural retrofitting and restoration of key hydraulic infrastructure at the Sunkoshi Hydropower Station—including the barrage, intake structures, and control room. The objective was to enhance operational safety, address long-term wear and tear, and improve the integrity of civil components critical to water diversion and power generation.
This retrofitting was executed through systematic assessment, surface restoration, and specialized grouting and mortar applications, conducted under strict quality supervision by the consultant and NEA's CMG team.
Client
Nepal Electricity Authority (NEA)
Location
Lamosanghu, Sindhupalchowk, Nepal
Consultant
JVNL – a joint venture between Norconsult AS and Lahmeyer International GmbH
Contractor
Sinohydro Corporation
Project status
Completed
The project entailed the structural retrofitting and restoration of key hydraulic infrastructure at the Sunkoshi Hydropower Station—including the barrage, intake structures, and control room. The objective was to enhance operational safety, address long-term wear and tear, and improve the integrity of civil components critical to water diversion and power generation.
This retrofitting was executed through systematic assessment, surface restoration, and specialized grouting and mortar applications, conducted under strict quality supervision by the consultant and NEA's CMG team.
Client
Nepal Electricity Authority (NEA)
Location
Lamosanghu, Sindhupalchowk, Nepal
Consultant
JVNL – a joint venture between Norconsult AS and Lahmeyer International GmbH
Contractor
Sinohydro Corporation
Project status
Completed
Rust Treatment and Reinforcement Passivation:
Crack Injection and Structural Repair:
Surface Mortar Application: